The following amendments to the 2018-2021 Metropolitan Transportation Improvement Program are proposed:

21393 – Springfield
Mill Street: A Street to Centennial Boulevard
Mill Street reconstruct from S. A Street to Centennial Boulevard
2020 planning phase to be canceled ($158,999.22 STBG)
2020 preliminary engineering phase to be increased by $158,999.22 STBG, new phase total = $1,731,380.32

19773 – Eugene
South Willamette Street enhancement
Pavement preservation, ADA improvements, streetscape/bike/pedestrian enhancements
Add $1,531,929.22 of local funds to 2020 CN phase. New CN phase total $7,437,970.60

20144 – ODOT
OR126B: S 20th Street – 75th Street (Springfield)
Design for a future construction project to provide safety solutions identified by the Springfield Main Street Safety Planning Phase.
Cancel the 2021 Right of Way Acquisition phase ($50,000 ACP0)