Proposed Amendments to 18-21 MTIP
Proposed Amendments to 18-21 MTIP
Public comment opportunity for proposed amendments to the 2018 - 2021 Metropolitan Transportation Improvement Program
Views4
Interactions0
Closed
Share
Share

The following proposed amendments to the 18-21 MTIP are currently open for public comment through August 20, and will be considered by the Transportation Planning Committee at their August 21 meeting.

I. Convert Funds (21396; Springfield) requested 7/19/19
Action requested – TPC approval
SRTS Crossing Improvements
Design and construction of crossing improvements at Jasper Road at Dondea St.
Total Current Est.: $125,000 (STBG)
• Convert federal STBG funds to State Funds (SFLP)


II. Convert Funds (20174; Springfield) requested 7/19/19
Action requested – TPC approval
Gateway St at Kruse Way intersect improvements
Install rectangular rapid flashing beacon with median island. Install traffic separators to protect the designated left turn on the south leg of Gateway at the Gateway/Beltline signalized intersection.
Total Current Est.: $231,300 (HSIP)
• Convert federal HSIP funds to State Funds (SFLP)


III. Slip Phases (21327; Coburg) requested 7/22/19
Action requested – TPC approval
Coburg Loop- N. Coburg Industrial Way
Construct shared-use path along west side of N Coburg Industrial Way from Sarah Lane Connector to Wetland Park
Total Current Est.: $699,877 (STBG)
• Slip PE phase from 2019 to 2020
• Slip CN phase from 2020 to 2021


IV. Slip Phase (21477; Lane County) requested 7/29/19
Action requested – TPC approval
Beaver Hunsaker Corridor Safety Express
Resurface roadway with new markings providing pedestrian space with vertical delineators on south side of Hunsaker Ln; install RRFB on Hunsaker Ln at Taito St; new separated path on east side of Beaver St to existing path at Division Ave.
Total Current Est.: $668,672.68 (HIP)
• Slip PE phase from 2019 to 2020


V. Slip Phases (21447;) requested 8/2/19
Action requested – TPC approval
Signal enhancements on various signals on local roads.
Total Current Est.: $2,033,100
City of Springfield signal enhancements (local roads)
• Slip PE phase from 2019 to 2020
• Slip RW phase from 2020 to 2021


VI. Add Funds (20165; Eugene) requested 8/5/19
Action requested – TPC approval
13th Ave: Lincoln St to Alder St (Eugene)
Safety projects at various locations including illumination, intersection work, bike/pedestrian improvements, ADA upgrades, signal work, signs, striping, medians; Construct two-way protected bikeway along 13th Avenue from Alder Street to Olive Street.
Total Current Est.: $3,004,654.52 (HSIP, STBG)
• Add $395,862.91 local funds to CN
• $97,600 HSIP to be added to CN from canceled RW and UR (already approved)
• New Total Est.: $3,498,117.43


VII. Cancel Project (21395, 21174; Springfield) requested 8/7/19
Action requested – TPC approval
21395 - 19 St and Marcola Rd intersection design
Analyze design concepts to identify appropriate intersection treatment.
Total Current Est.: $100,000 (CMAQ)
• Cancel PL phase ($100,000 CMAQ)
• Project to be completed with local funds

21174 - S. 28th Street dust mitigation (Springfield)
Pave gravel portion of S. 28th St from S. F St to city limits; pave shoulders and driveway approaches and improve surface drainage.
Total Current Est.: $1,825,872.76 (CMAQ, local)
• Add $89,156.36 (CMAQ + match) to CN phase
• New Total Est.: $1,915,029.12