I. Funding Changes per June OTC (19490; ODOT) requested 7/10/18
Action requested – TPC approval
STIP Key# 19490 – OR569: BELTLINE @ DELTA HIGHWAY - INTERCHANGE
Description: Ramp and Interchange Improvements
Total Project Est.: $8,500,000 (NHPP, HB2001B Bond Funds - JTA)
• Reduce PE phase HB2001B funding from $6,000,000 to $2,000,000
• Add FFY19 UR phase with $350,000 (HB2001B)
• Add FFY19 CN phase with $23,650,000 (HB2001B)
• New Total Project Est.: $28,500,000
• No change to Federal (NHPP) funds

II. Slip multiple phases (20209; Springfield) requested 6/21/18
Action requested – TPC approval
STIP Key# 20209 – OR126B @ 54TH St. (Springfield)
Description: Install left turn lanes on 54th St. Modify left turn signal heads to "flashing yellow arrow" on 54th St approaches. Implement a pedestrian crossing safety timing feature with the flashing yellow left turn arrow. Install intersection lighting.
Total Project Est.: $1,641,300 (HSIP)
• Slip PE phase from 2018 to 2019
• Slip RW phase from 2018 to 2019
• Slip UR phase from 2018 to 2019

III. Convert to State Funded Local Project (20236; Springfield) requested 6/25/18
Action requested – TPC approval
STIP Key# 20236 – Filling the gaps – Safe Routes to School (Springfield)
Description: Cover the community notification, engineering, and construction costs necessary to produce completed sidewalk projects across Springfield for the Safe Routes to School (SRTS) program.
Total Project Est.: $638,000 (STBG-Flex; City of Springfield)
• Advance PE phase from 2019 to 2018
• Advance RW phase from 2019 to 2018
• Advance CN phase from 2020 to 2018
• Convert all federal funds to state funds
• No change to Total Project Est.

IV. Slip CN phase to FFY19 (21251; ODOT) requested 7/3/18
Action requested – TPC approval
STIP Key# 21251 – OR126: Mohawk Blvd (Springfield)
Description: Design and construct ADA compliant curb ramps and pedestrian signals per the Americans with Disability Act.
Total Project Est.: $250,000 (STBG-Flex, State Funds)
• Slip CN phase from 2018 to 2019

V. Convert to State Funded Local Project (20143; Eugene) requested 7/24/18
Action requested – TPC approval
STIP Key# 20143 – River Rd at River Ave (Eugene)
Description: Install raised traffic separators to protect designated left turn lanes on all approaches at the intersection except the north leg.
Total Project Est.: $160,600 (HSIP)
• Advance UR phase from 2019 to 2018
• Advance CN phase from 2021 to 2018
• Convert all federal funds to state funds
• No change to Total Project Est.