Public Hearing & Public Comment Period for Proposed Amendment to Metropolitan Transportation Improvement Program (MTIP)
Public Hearing & Public Comment Period for Proposed Amendment to Metropolitan Transportation Improvement Program (MTIP)
Public Hearing & Public Comment Period for Proposed Amendment to Metropolitan Transportation Improvement Program (MTIP)
Views7
Interactions0
Closed
Share
Share

Public hearing will take place 11:30AM April 4, 2019 at the Metropolitan Policy Committee (MPC meeting, held at the City of Springfield Justice Center 2nd Floor Meeting Room (344 A St., Springfield). Public Comments will be accepted through April 28.

Springfield was approved $1,924,709 of STBG funds for 28th Street pavement
preservation from Main Street to Olympic Street (STIP Key 21394). Costs for this
project are coming in much higher than originally estimated, especially for the ADA
improvement components. Because of this the City would like to cancel this project
and move the funds to other priorities.

The Virginia-Daisy Surface Preservation project (STIP Key 19917) was supported by
MPC with STBG funding in 2016. Since then the project funds have been converted
from Federal to State funding as part of ODOT’s State Funded Local Program. City of
Springfield requests that $1,672,954 (STBG) and $191,477.07 (required local match)
be added to Construction phase of this project from the cancelled 28th Street project.
These needed improvements have become a priority for the City.

Finally, the Mill Street reconstruct project, from A Street to Centennial Boulevard
(STIP Key 21393), also supported by MPC with STBG funding, currently includes an
overmatch amount of $616,754.73 for construction, provided by the City of Springfield. This amendment would replace $251,755 of Springfield’s overmatch with federal
STBG funds. The total project funding amount would remain unchanged.

More Info:
Cover Memo
Current Projects vs Amended Projects [proposed]